Lecture –6

 

 

 

 

 

 

Lecture –6

Production Planning & Control

 

 

 

 

 

 

 

 

    Topics Covered:

 

n Meaning of production planning 

n Typical objectives of production planning

n The Production Planning Process/Steps/Stages 

n Meaning of Production Control

n Steps/Mechanisms of Production Control

n Problems of Production Planning & Control

             n Model Questions

 

 

 


nMEANING OF PRODUCTION PLANNING

Production Plan is a statement of production rates, workforce levels and inventory holding based on estimates of customer requirements and capacity limitations. It is essentially a “Big Picture” approach to planning. This statement is time-phased, meaning that the plan is projected for several time periods into the future.

A production plan must balance conflicting objectives involving customer service, workforce stability, cost and profit. A production plan is developed to guide more detailed planning that eventually leads to master plan which is shown below:

 

 

 

                 Figure: Layout of Production Planning

 

 

 

nTYPICAL OBJECTIVES OF PRODUCTION PLANNING

 

Six objectives usually are considered during development of a production plan and conflicts among them may have to be resolved:

1.   Minimize Cost/ Maximize Profits:

If customer demand is not affected by the plan, minimizing cost will also maximize profits.

 

2.   Maximize Customer Service:

Improving delivery time and on-time delivery may require additional work force, machine capacity or inventory resources.

 

3.   Minimize Inventory Investment:

Inventory accumulations are expensive because the money could be used for more productive investments.

 

4.   Minimize Changes in Production Rate:

Frequent changes in production rates can cause difficulties in coordinating the supplying of materials and require production line re-balancing.

 

5.   Minimize Changes in Production Workforce Levels:

Fluctuating workforce levels may cause lower productivity because new employees typically need time to become fully productive.

 

6.   Maximize Utilization of Plant & Equipment:

Processes based on a line flow strategy require uniformly high utilization of plant and equipment.

 

 

 

nTHE PRODUCTION PLANNING PROCESS

At the time of preparing a production plan, the following steps can be followed:

 

     1.  Determining demand requirement

     2. Identifying alternatives constraints and cost

3. Preparing an acceptable plan

              4. Implementing and updating the plan

 

The process can be shown through the following figure:

 

 

 

Figure: The Production Planning Process

 

 

 

 

 

·       Determining Demand Requirement:

                The first step in the Production Planning Process is to determine the demand requirement for each period for the planning horizon. For Production Plans, the requirement represents the demand for finished goods and the external demand for replacement parts. The planner can deceive future requirements for finished goods from backlogs (customer’s order that promised for delivery) or from forecasts for product families made to stock. 

·       Identifying Alternative Constraints & Costs:

                   The second step is to identify the alternative constraints and cost for the plan. Alternatives represent the consideration for solving the questions like what options should be considered in responding to uneven demand and how can demand be leveled to reduce operating cost.

                 Constraints represent physical limitations or managerial policies associated with Production Plan. The planner usually considers several types of cost when preparing Production Plans such as regular time cost, overtime cost, hiring and layoff cost, inventory holding cost and backorder (an order that the customer expected to be filled immediately and delivered as soon as possible) and stockout (an order that is lost and causes the customer to go elsewhere) cost.

·       Preparing an Acceptable Plan:

                   The third step is to prepare an acceptable plan. Developing an acceptable plan is an iterative (repeat) process. So a tentative plan is developed to start. The plan must then be checked against constraints and evaluated in term of strategic objectives. When the plan is acceptable to the representatives from all functional areas, implementation can begin; otherwise a new prospective plan must be developed.

·       Implementing & updating the plan:    

                   Implementation requires the commitment of managers in functional areas. Acceptance of the plan does not necessarily mean that everyone is in total agreement, but it does imply that everyone will work to achieve it.

nMEANING OF PRODUCTION CONTROL

Production control is the observation of production activities whether these are conducted according to established standards, finding deviations and taking corrective actions. The purpose of production control is to produce product:

Ø  at minimum cost

Ø  in the best methods

Ø  of right time

Ø  of right quality

According to Alford and Bangs,

“Production control is the highest efficiency in production is obtained by manufacturing the required quantity of product of required quality of the required time by the best and cheapest method.”   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

nSTEPS / MECHANISMS / STAGES / PROCESS OF PRODUCTION CONTROL:

 

Production control is done on the basis of production plan. So production plan is started as the primary requirement of production control. The stages of production control are as follows- 

Figure: Steps in Production Control

 

1.Routing:

Routing includes the planning of where and by whom the work shall be done, the determination of the path that the work shall follow and the necessary sequence of operations. It forms the basis for the most of scheduling and dispatching technique. Routing is the determination of the way in which the transformation process of raw materials is done and determining the chronological sequences of activities and process to be followed in producing a particular manufacturing lot.

 

 

 

2.Scheduling:

Scheduling is the determination of time that should be required to perform each operation and also the time necessary to perform the entire series as routed. It is a plan that specifies time periods for completing specify activities. It generally tells the start and due dates so that job can be completed when they are promised or needed.

 

3.Despatching:

The third logical step of Production control is despatching. Despatching is the routing of setting production activities in motion through the release of order and instructions in accordance with previously planned times and sequence, embodied on route sheets and schedule charts.

 

4.Follow – up:

Follow up is the final stage of production control after routing, scheduling and despatching. Follow – up is basically the observation of activities whether these are conducted according to the production plan. Finally, Follow – up can be defined as the process of observation concentrated on the activities if these are conducted as on the production plan, finding out deviations and taking corrective actions.

 

 

 

 

 

 

 

 

 

 

 

 

nPROBLEMS OF PRODUCTION PLANNING & CONTROLLING:

 

The problems of Production Planning and controlling can be divided broadly in two categories:

 

1.   Long-term problems:

a.  Selection of equipment of process

b.  Production design of items processed

c.   Determination of optimum size of the factory

d.  Finding out suitable locations

e.   Job designing

f.     Plant layout

g.  Production forecast

h.   Preparation of master schedule

2.   Short-term problems:

a. Preparing procurement schedule

b. Preparing personal schedule

c. Inventory control

d. Production control

e. Preparing alternative inventory plans for production

f. Maintenance of the system

g. Quality control

h. Cost control

 

 

Model Questions

 

1.    What is the meaning of production planning?

2.    What are the typical objectives of production planning?

3.    Describe the stages of Production Planning Process. 

4.    What is Production Control?

5.    What are the steps/Mechanisms of Production Control? Discuss.

6.    State the Problems of Production Planning & Control.

 

===

No comments:

Post a Comment